Friday, October 12, 2018

*UPDATE - 5:00 PM* Campus Network Maintenance Window - Saturday, October 20, 2018 7:00AM - 11:00AM

WHAT: Campus Network Maintenance

WHEN: Saturday, 10/20/2018 Duration: 7:00 AM - 11:00 AM

WHERE: Campuswide

Current Status: Scheduled

Description:
*5:00 PM UPDATE*
All known issues affecting production systems have been addressed or are pending final verification.  I&TS will continue to monitor services throughout the weekend to confirm service stability.

*2:00 PM UPDATE*
Our work completed just before 11:00 AM this morning.  Unfortunately, a couple of systems (most notably Banner) seem to have suffered ill-effects from the maintenance work.  The I&TS team is actively testing and troubleshooting all of affected systems and expects to have normal service restored soon.  We apologize for the delay in service restoration.

*ORIGINAL POST*
I&TS will be performing a series of network equipment maintenance tasks including equipment changes as well as firmware updates on Saturday, October 20, 2018.  This work will cause intermittent disruption of connections to most campus buildings periodically throughout maintenance period including brief disruptions of connectivity from/to off-campus.

The bulk of the work, including the most substantial service impacting activities, is scheduled for the first part of the maintenance window with that majority expected to be complete by the half-way mark of the window.

Service(s) Impacted: Campus Network & Internet connectivity

Next Update: Following completion of work.

Check https://www.plu.edu/status/ for periodic updates.

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.